BRIEF DESCRIPTION

This was a NAVFAC Southwest contract to design and install a new steam piping system for the steam cleaning facility S575 at MCLB, Barstow, California. This facility provides cleaning, degreasing and decontaminating of a wide array of military vehicles. KEAR installed a new system including new header pipe, distribution lines to each bay, new steam guns and a new transmission line to an adjacent building. This design build project is scheduled for completion in February of 2018. Photos were not allowed on this project.

TITAN provided a Quality Control Manager on this project.

SSHO SCOPE OF WORK

  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Enforced USACE EM 385-1-1 and held the project to OSHA standards
  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Managed all phases of safety control
  • Conducted daily safety inspections
  • Conducted daily safety briefings and weekly toolbox talks
  • Kept list of deficient safety items and maintained list until all safety deficiencies were addressed
  • Coordinated with USACE QA on site all safety items
  • Ensured public safety with additional warning signs and barriers
  • Maintained OSHA 300 Form and Daily Production reports
  • Kept photo logs of all safety issues
  • Attended pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings
  • Enforced accepted APPS and AHAs
  • Spoke to local businesses and discussed safety issues with their patrons with our current operations

AT A GLANCE

Project Type Government
TITAN Role Quality Control (QC) Manager
Client Southern Marine Construction Co.
Completion Date April 2018
Contract Value $469.7k