POM B-829 Stucco Repair - Monterey, CA

W91238-18-C-0028

BRIEF DESCRIPTION

Building 829 is a barracks complex within the Presidio of Monterey (POM) that has been identified as having mold on some of the north and west-facing interior walls and insulation.

Building 829 is broken into four separate buildings, referred to as “quads”. These quads are separated by connected walkways. Building 829 required  work on all four quads and walkways. Ironwood Commercial Builders removed the existing stucco finish on all sides of the buildings, and replaced with a new Exterior Insulation and Finish System installed over exterior applied glass mat reinforced gypsum sheathing, all accent bands/motifs were re-installed to match original. New interior surfaces received level 5 finish, textured to match existing walls, and new paint.

TITAN provided a Quality Control Manager to the project.

QC MANAGER SCOPE OF WORK

  • Procedures for tracking preparatory, initial, and follow-up control phases; control, verification, and acceptance tests including documentation
  • Coordination of project logistics, materials and equipment
  • Managing the day-to-day quality control activities
  • Kept designated personnel and management staff apprised of status of work
  • Ensured all reports were prepared and submitted in accordance with the QC Plan, including the Daily Quality Control Reports
  • Maintained all the project quality control files
  • Reported and logged any work not meeting Spec requirements
  • Recorded all data in QCS database

AT A GLANCE

Project Type Government
TITAN Role Quality Control (QC) Manager
Client Ironwood Commercial Builders
Contract Price 3.1m