Maintenance Dredging Matanzas Inlet, FL

Contract: W912EP-19-C-0020

Play Video

BRIEF DESCRIPTION

This project entailed dredging approximately 185,200 cubic yards of material from Reach I of the ICWW in Flagler County, Florida.

The ICWW maintenance dredging area extends from ICWW Cut F-2 STA
32+00 through ICWW Cut-F10 STA 12+52. This maintenance work will include excavation of the ICWW channel to an elevation of -14 feet (ft) mean lower low water (MLLW) (project depth of -12 feet and 2-foot allowable overdredge).

All dredged material was offloaded at the District-owned ±44-acre dredged material management area (DMMA) FL-3 located in Palm Coast, Florida.

Even though Hurricane Dorian came very close to this particular location, the project lost very little time.

TITAN provided an SSHO and QC Manager to the project.

AT A GLANCE

Project Type FIND
TITAN Role Site Safety & Health Officer (SSHO) & Quality Control (QC) Manager
Client Southwind Construction
Contract Price $5,898,389

SSHO SCOPE OF WORK

  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Enforced USACE EM 385-1-1 and held the project to OSHA standards
  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Managed all phases of safety control
  • Conducted daily safety inspections
  • Conducted daily safety briefings and weekly toolbox talks
  • Kept list of deficient safety items and maintained list until all safety deficiencies were addressed
  • Coordinated with Government QA onsite for all safety items
  • Ensured public safety with additional warning signs and barriers
  • Maintained OSHA 300 Form and Daily Production reports
  • Kept photo logs of all safety issues
  • Attended pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings
  • Enforced accepted APPS and AHAs
  • Spoke to local businesses and discussed safety issues with their patrons with our current operations

QUALITY CONTROL MANAGER SCOPE OF WORK

  • Procedures for tracking preparatory, initial, and follow-up control phases; control, verification, and acceptance tests including documentation
  • Coordination of project logistics, materials and equipment
  • Managing the day-to-day quality control activities
  • Kept designated personnel and management staff apprised of status of work
  • Ensured all reports were prepared and submitted in accordance with the QC Plan, including the Daily Quality Control Reports
  • Maintained all the project quality control files
  • Reported and logged any work not meeting Spec requirements
  • Recorded all data in QCS database