Dike Rehabilitation – Miami, FL

W912EP-13-C-0027

BRIEF DESCRIPTION

This project consisted of the replacement of existing dike culverts 5 and 5A on Lake Okeechobee. Culverts were replaced with a triple 10 x 10 cast in place concrete box with a liner pipe. Construction activities included: construction of a surcharge mound, demolition and removal of existing structures, installation of temporary earth and sheet pile cofferdams, by-pass pumping, construction of a new cast-in-place reinforced concrete structure. An internal drainage system and cutoff wall was be constructed within the embankment

TITAN Provided the Project SSHO

SSHO SCOPE OF WORK

  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Enforced USACE EM 385-1-1 and held the project to OSHA standards
  • Maintained MSDS to ensure no hazardous items were brought onto jobsite
  • Managed all phases of safety control
  • Conducted daily safety inspections
  • Conducted daily safety briefings and weekly toolbox talks
  • Kept list of deficient safety items and maintained list until all safety deficiencies were addressed
  • Coordinated with USACE QA on site all safety items
  • Ensured public safety with additional warning signs and barriers
  • Maintained OSHA 300 Form and Daily Production reports
  • Kept photo logs of all safety issues
  • Attended pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings
  • Enforced accepted APPS and AHAs
  • Spoke to local businesses and discussed safety issues with their patrons with our current operations

AT A GLANCE

Project Type Government-USACE
TITAN Role Site Safety & Health Officer (SSHO)
Client Thalle Construction Company
Completion Date November 2018
Contract Value $800,000